Ontario Wind
EWR is currently involved with the construction of a wind farm in Ontario.
- 84% of the cable is installed and has been pulled into 53 of 87 turbines
- 76 of 87 turbines have now been delivered, not including blades​
- 61 of 87 turbines have now been erected through the nacelle and hub
- 97% of the foundations for the transmission line are complete and 58% of the line is strung (60.5 of 104 km)
The project is expected to be completed in 2019. The wind farm is expected to produce 300 MW of power.